Parts of Metro Manila, Cavite, Laguna will experience power interruptions from June 15 to 16 to due to scheduled maintenance activities.
In an advisory posted on its website, Manila Electric Company (Meralco) said there will be relocation of primary facilities along Gen. Luna Street in Barangay Poblacion, Makati City on June 15.
Affected between 9 a.m. and 2 p.m. are:
There will also be an installation and replacement of facilities, and line reconstruction and reconductoring works along Arnaldo Highway in Gen. Trias City, Cavite from June 15 to 16.
Affected between 11:30 p.m. and 11:59 p.m., Saturday, June 15, and between 6 a.m. and 6:30 a.m., Sunday, June 16 are:
Affected between 12:01 a.m. and 6 a.m., Sunday, June 16 are:
Meralco will also be replacing badly leaning poles and line reconductoring works along F. B. Harrison Street in Pasay City on June 16.
Affected between 8:30 a.m. and 9 a.m. and then between 3 p.m. and 3:30 pm are:
Affected between 8:30 a.m. and 3:30 p.m. are:
There will be line reconstruction works along Abbey Road in Barangay Sauyo, Novaliches, Quezon City on June 16.
Affected between 9 a.m. and 11:30 a.m. are:
Meralco will also be conducting preventive maintenance and testing works in Meralco – CIPP substation, Calamba, Laguna on June 16.
Affected between 9 a.m. and 5 p.m. are:
There will also installation and replacement of poles, and line reconductoring works along Mamatid Road in Barangay Mamatid, Cabuyao City, Laguna on June 16.
Affected between 12:01 a.m. and 5 a.m. are:
—AOL, GMA Integrated News